Project Details

  • AMENITY
    1. Elegant A/C lobby and reception area
    2. Terrace party area
    3. Fully furnished air conditioned guest suites.
    4. Provision for Internet connectivity for each apartment
    5. Fitness centre with most modern equipment
    6. A/C Multipurpose hall
    7. Reading room and provision for reference library
    8. Intercom facility
    9. Children’s play area
    10. Provision for Cable TV connection in each apartment
    11. Name Boards
    12. Generator back - up for lifts, water pumps, common lighting and designated points in each apartment.
    13. Sewage system
    14. Security cabin
    15. Changing room for drivers and servants
    16. Toilets for drivers and servants
    17. Automatic gate control system for entry / exit
    18. Solar assisted lighting in designated points of common areas
    19. CCTV camera in entrance and gate portion
  • SPECIFICATIONS
    Structure
    RCC framed structure designed for higher seismic consideration with pile foundation

    Flooring
    Superior quality Granite flooring in entrance lobby.Elegant Vitrified tilesfor the remaining area, except toilets and staircase.
    Doors
    Polished teak wood frame and shutter for entrance door and moulded shutters for internal doors with hard wood frames. Hardwood frames with treated flush door of one side resin coating for toilets. Internal doors and frames painted with superior quality synthetic enamel paint.
    Staircase
    Flooring with vitrified rustic tiles and hand rails in stainless steel.
    Kitchen & Work Area
    Counter with granite top and Superior Quality stainless steel sink in kitchen. Glazed tiles above the counter to a height of 40cms. Single bowl sink with granite top in work area. Provision for water purifier and dish washer.
    Electrical
    All wiring with superior quality copper wires inside apartments including PVC conduits of ISI standards. Power plugs with adequate light and fan points. Points controlled by ELCB and MCB with independent KSEB meter. Branded modular switches of Legrand or equivalent quality. Provision for Washing machine, Fridge etc. and provision for internet connection in one bed room.

    Air-Conditioning.
    Wired provision in all bedrooms and living.
    Toilets
    Premium quality anti-skid ceramic tiles for the floor and modern glazed tiles for wall up to door height. Geyser provision and health faucet in all toilets except in servant
    Generator
    Generator backup for elevators, water pumps and designated points in each apartment and common area light points.
    Fire safety
    Fire protection systems as per rules.

    Painting
    Premium quality putty finish with plastic emulsion for internal walls & ceilings. Balcony handrails painting with enamel paint. Outside walls painting with superior quality weather shield paint.
    Sanitary ware & CP fittings
    Branded sanitary fixtures matching with tiles, wall mount closet of Roca/American Standards or equivalent type with concealed flushing cistern. CP fitting of `Jaquar` or equivalent type

    Windows
    Powder coated aluminium frame with glazed sliding shutters and MS safety grills.
    Cable TV
    Provision for cable TV connection in Living and master bedroom (subject to then prevailing Government rules).

    Water supply
    Water supply arrangements through sump and overhead tank. individual water meter for each apartment

    Telephone
    Wiring for telephone in Living and Master bedroom.
    Balcony
    Flooring with anti-skid ceramic/vertified tiles and MS balusters with GI top rail.
  • Location Map
    LOCATION MAP

April

  10 Apr 2019

1 Basement floor slab to roof slab concreting Completed
2 Block work in first to Tenth floor Completed
3 Stair head room & over head tank concreting In progress
4 Electrical wall chasing up to Sixth floor Completed
5 Door frame fixing In progress
6 Balcony handrail fixing in first floor Completed
7 External duct works In progress
8 External plastering works In progress
9 Fire fighting works In progress
10 Plumbing works In progress

JANUARY

  17 Jan 2019

Basement floor slab to Eleventh floor slab concreting Completed
Twelfth floor column concreting 80% completed
Twelfth floor slab concreting Completed
Block work in first to Eighth floor Completed
Block work in Ninth & tenth floor In progress
Electrical wall chasing up to third floor Completed
Door frame fixing In progress
Balcony handrail fixing in first floor Completed

November

  21 Nov 2018

Basement floor slab to Tenth floor slab concreting Completed
Retaining wall works Completed
Tenth floor column concreting Completed
Block work in first to seventh floor Completed
Block work in Eighth floor In progress
Electrical wall chasing in first floor Completed

September

  06 Oct 2018

1 Basement floor slab to seventh floor slab concreting Completed
2 Retaining wall works Completed
3 Seventh floor column concreting Completed
4 Eighth floor slab concreting Completed
5 Block work in first to third floor Completed
6 Block work in fourth & fifth floor In progress

JULY

  14 Jul 2018

1 Foundation works Completed
2 Basement floor slab to fifth floor slab concreting Completed
3 Retaining wall works Completed
4 Fifth floor column concreting Completed
5 Sixth floor slab concreting Completed
6 Block work in first floor Completed

JUNE

  26 Jun 2018

1 Foundation works Completed
2 Basement floor slab to fourth floor slab concreting Completed
3 Retaining wall works Completed
4 Fourth floor column concreting Completed
5 Fifth floor slab concreting Completed
6 Block work & plastering in first floor In progress

MAY

  15 May 2018

1 Foundation works Completed
2 Basement floor slab to third floor slab concreting Completed
3 Retaining wall works Completed
4 Third floor column concreting Completed
5 Fourth floor slab concreting Completed
6 Block work & plastering in first floor In progress

APRIL

  17 Apr 2018

1. Foundation works Completed
2. Basement floor slab to second floor slab concreting Completed
3. Retaining wall works Completed
4. Second floor column concreting Completed
5. Third floor slab concreting Completed

MARCH

  20 Mar 2018

1 Foundation works Completed
2 Basement floor slab to first floor slab concreting Completed
3 Retaining wall works Completed
4 First floor column concreting Completed
5 Second floor slab concreting Completed

February

  02 Feb 2018

Work description Current Status
1 Foundation works Completed
2 Basement floor slab Completed
3 Retaining wall works Completed
4 Ground floor slab Completed
5 Ground floor column concreting Completed
6 First floor slab concreting Completed

December

  30 Dec 2017

1 Foundation Works Completed
2 Basement floor slab Completed
3 Retaining wall works 75 % completed
4 Ground floor slab Completed
5 Ground floor column concreting 50 % completed

August

  11 Aug 2017

1 Piling works Completed
2 Retaining wall works In progress
3 Pile cap & grade beam works In progress
4 Second basement floor column concreting In progress
5 First basement floor slab concreting In progress

01.07.2017

  01 Jul 2017

1 Piling works 85% completed
2 Pile chipping works In progress
3 Retaining wall works In progress
4 Pile cap & grade beam works In progress
5 Column reinforcement works In progress

05.05.2017

  11 May 2017

1 Piling works 60% completed
2 Pile chipping works In progress

05.04.2017

  05 Apr 2017

Piling works 35% completed

Work Status As On 05.03.2017

  05 Mar 2017

1 Piling Works Commenced
2 Retaining Wall Work – Rear Side Completed
3 Compound Wall Works - Rear Side Completed

Work Status As On 05.02.2017

  05 Feb 2017

1 Piling works Commenced
2 Retaining wall work – rear side Completed
3 Pile load test Completed
4 Compound wall works - rear side Completed

04.01.2017

  04 Jan 2017

1 Piling works Commenced
2 Retaining wall work – rear side In progress
3 Pile load test In progress