1 Basement floor slab to roof slab concreting Completed
2 Block work in first to Tenth floor Completed
3 Stair head room & over head tank concreting In progress
4 Electrical wall chasing up to Sixth floor Completed
5 Door frame fixing In progress
6 Balcony handrail fixing in first floor Completed
7 External duct works In progress
8 External plastering works In progress
9 Fire fighting works In progress
10 Plumbing works In progress
Basement floor slab to Eleventh floor slab concreting Completed
Twelfth floor column concreting 80% completed
Twelfth floor slab concreting Completed
Block work in first to Eighth floor Completed
Block work in Ninth & tenth floor In progress
Electrical wall chasing up to third floor Completed
Door frame fixing In progress
Balcony handrail fixing in first floor Completed
Basement floor slab to Tenth floor slab concreting Completed
Retaining wall works Completed
Tenth floor column concreting Completed
Block work in first to seventh floor Completed
Block work in Eighth floor In progress
Electrical wall chasing in first floor Completed
1 Basement floor slab to seventh floor slab concreting Completed
2 Retaining wall works Completed
3 Seventh floor column concreting Completed
4 Eighth floor slab concreting Completed
5 Block work in first to third floor Completed
6 Block work in fourth & fifth floor In progress
1 Foundation works Completed
2 Basement floor slab to fifth floor slab concreting Completed
3 Retaining wall works Completed
4 Fifth floor column concreting Completed
5 Sixth floor slab concreting Completed
6 Block work in first floor Completed
1 Foundation works Completed
2 Basement floor slab to fourth floor slab concreting Completed
3 Retaining wall works Completed
4 Fourth floor column concreting Completed
5 Fifth floor slab concreting Completed
6 Block work & plastering in first floor In progress
1 Foundation works Completed
2 Basement floor slab to third floor slab concreting Completed
3 Retaining wall works Completed
4 Third floor column concreting Completed
5 Fourth floor slab concreting Completed
6 Block work & plastering in first floor In progress
1. Foundation works Completed
2. Basement floor slab to second floor slab concreting Completed
3. Retaining wall works Completed
4. Second floor column concreting Completed
5. Third floor slab concreting Completed
1 Foundation works Completed
2 Basement floor slab to first floor slab concreting Completed
3 Retaining wall works Completed
4 First floor column concreting Completed
5 Second floor slab concreting Completed
Work description Current Status
1 Foundation works Completed
2 Basement floor slab Completed
3 Retaining wall works Completed
4 Ground floor slab Completed
5 Ground floor column concreting Completed
6 First floor slab concreting Completed
1 Foundation Works Completed
2 Basement floor slab Completed
3 Retaining wall works 75 % completed
4 Ground floor slab Completed
5 Ground floor column concreting 50 % completed
1 Piling works Completed
2 Retaining wall works In progress
3 Pile cap & grade beam works In progress
4 Second basement floor column concreting In progress
5 First basement floor slab concreting In progress
1 Piling works 85% completed
2 Pile chipping works In progress
3 Retaining wall works In progress
4 Pile cap & grade beam works In progress
5 Column reinforcement works In progress
1 Piling Works Commenced
2 Retaining Wall Work – Rear Side Completed
3 Compound Wall Works - Rear Side Completed
1 Piling works Commenced
2 Retaining wall work – rear side Completed
3 Pile load test Completed
4 Compound wall works - rear side Completed
1 Piling works Commenced
2 Retaining wall work – rear side In progress
3 Pile load test In progress