1 Entire Structural works of the building Completed
2 Block work from third to nineteenth floor Completed
3 Ceiling plastering from first to nineteenth floor Completed
4 External plastering : Rear, Left & Right sides - Completed
: Front side - In progress
5 Duct works : Rear, Left & Right sides-Completed
: Front side - 90% Completed
6 Internal wall plastering 80% Completed
7 Electrical wall chasing works 90 % Completed
8 Internal fire fighting works-5th to 10th floor Completed
9 Internal plumbing works 75% Completed
(Wall chasing & concealed line works)
10 Internal putty works (1st coat) In progress
11 Water proofing works in sump In progress
Terrace floor slab concreting Completed
Terrace floor column concreting Completed
Block work from third to Eighteenth floor Completed
Ceiling plastering from third to Eighteenth floor Completed
External plastering
Rear side up to 11th floor - Completed
12th to terrace floor - In progress
Left side up to 11th floor - Completed
Right side up to 11th floor- Completed
Duct works
- Left side up to 11th floor -Completed
- Right side up to 11th floor -Completed
Rear side -Completed
Internal wall plastering
- 5th to 10th floor -Completed
- 11th Floor -In progress
Electrical wall chasing works
- 4th to 11th floor -Completed
- 3rd Floor In progress
Carpentry works In progress
Balcony handrail fabrication works In progress
First to eighteenth floor slab concreting Completed
Eighteenth floor column concreting 40% completed
Block work from third to Fourteenth floor Completed
Ceiling plastering from third to fifteenth floor Completed
External plastering
- Rear side up to 11th floor - In progress
- Left side up to 11th floor - Completed
- Right side up to 11th floor - 85% completed
Duct works
- Left side up to 11th floor, Right side up to 11th floor -Completed
Internal wall plastering up to 11th floor -45% completed
Electrical wall chasing works up to 11th floor - 35% completed
1 First to fifteenth floor slab concreting Completed
2 Fourteenth floor column concreting Completed
3 Block work from third to Eleventh floor Completed
4 Ceiling plastering from third to thirteenth floor Completed
5 External plastering
- Rear & left side In progress
6 Duct works
- Left side -Completed
- Right side -In progress
Foundation works Completed
First to Eleventh floor slab concreting Completed
Eleventh floor column concreting Completed
Twelfth floor slab concreting Completed
Foundation works Completed
First to Tenth floor slab concreting Completed
Tenth floor column concreting Completed
Eleventh floor slab concreting Completed
1 Foundation works Completed
2 First to Nineth floor slab concreting Completed
3 Nineth floor column concreting Completed
4 Tenth floor slab concreting Completed
Foundation works Completed
Seventh floor column concreting Completed
First to eighth floor slab concreting Completed
Work description Current Status
1 Foundation works Completed
2 First to fifth floor slab concreting Completed
3 Fifth floor column concreting Completed
4 Sixth floor slab shuttering & reinforcement laying works In progress
1 Foundation works Completed
2 First to third floor slab concreting Completed
3 Fourth floor slab shuttering works In progress
1 Piling works Completed
2 Pile cap & grade beam works Completed
3 Ground floor column concreting Completed
4 Ground floor roof slab concreting In Progress
1 Piling works Completed
2 Pile chipping works Completed
3 Pile cap & grade beam works 50% completed