Project Details

  • AMENITIES
    1. Elegant A/C lobby and reception area
    2. Terrace party area
    3. Fully furnished air conditioned guest suites.
    4. Provision for Internet connectivity for each apartment
    5. Fitness centre with most modern equipment
    6. A/C Multipurpose hall
    7. Reading room and provision for reference library
    8. Intercom facility
    9. Children’s play area
    10. Provision for Cable TV connection in each apartment
    11. Name Boards
    12. Generator back - up for lifts, water pumps, common lighting and designated points in each apartment.
    13. Sewage system
    14. Security cabin
    15. Water supply system through sump and over head tank
    16. Changing room for drivers and servants
    17. Toilets for drivers and servants
    18. Automatic gate control system for entry / exit
    19. Solar assisted lighting in designated points of common areas
    20. CCTV camera in entrance and gate portion.
  • Specifications of Cordial Dhanuss
    1. Structure: RCC framed structure designed for higher seismic consideration with pile foundation

    2. Flooring: Superior quality Granite flooring in entrance lobby.Elegant Vitrified tilesfor the remaining area, except toilets and staircase.

    3. Doors: Polished teak wood frame and shutter for entrance door and moulded shutters for internal doors with hard wood frames. Hardwood frames with treated flush door of one side resin coating for toilets. Internal doors and frames painted with superior quality synthetic enamel paint.

    4. Staircase: Flooring with vitrified rustic tiles and hand rails in stainless steel.

    5. Kitchen & Work Area: Counter with granite top and Superior Quality stainless steel sink in kitchen. Glazed tiles above the counter to a height of 40cms. Single bowl sink with granite top in work area. Provision for water purifier and dish washer.

    6. Electrical: All wiring with superior quality copper wires inside apartments including PVC conduits of ISI standards. Power plugs with adequate light and fan points. Points controlled by ELCB and MCB with independent KSEB meter. Branded modular switches of Legrand or equivalent quality. Provision for Washing machine, Fridge etc. and provision for internet connection in one bed room.

    7. Air-Conditioning: Wired provision in all bedrooms and living.

    8. Toilets: Premium quality anti-skid ceramic tiles for the floor and modern glazed tiles for wall up to door height. Geyser provision and health faucet in all toilets except in servant

    9.Generator: Generator backup for elevators, water pumps and designated points in each apartment and common area light points.

    10. Fire safety: Fire protection systems as per rules.

    11. Painting: Premium quality putty finish with plastic emulsion for internal walls & ceilings. Balcony handrails painting with enamel paint. Outside walls painting with superior quality weather shield paint.

    12. Sanitary ware & CP fittings:Branded sanitary fixtures matching with tiles, wall mount closet of Roca/American Standards or equivalent type with concealed flushing cistern. CP fitting of `Jaquar` or equivalent type

    13.Windows:Powder coated aluminium frame with glazed sliding shutters and MS safety grills.

    14.Cable TV:Provision for cable TV connection in Living and master bedroom (subject to then prevailing Government rules).

    15.Water supply:Water supply arrangements through sump and overhead tank. individual water meter for each apartment

    16. Telephone:Wiring for telephone in Living and Master bedroom.

    17.Balcony:Flooring with anti-skid ceramic/vertified tiles and MS balusters with GI top rail.

April

  10 Apr 2019

1 Entire Structural works of the building Completed
2 Block work from third to nineteenth floor Completed
3 Ceiling plastering from first to nineteenth floor Completed
4 External plastering : Rear, Left & Right sides - Completed
: Front side - In progress
5 Duct works : Rear, Left & Right sides-Completed
: Front side - 90% Completed

6 Internal wall plastering 80% Completed
7 Electrical wall chasing works 90 % Completed
8 Internal fire fighting works-5th to 10th floor Completed

9 Internal plumbing works 75% Completed
(Wall chasing & concealed line works)

10 Internal putty works (1st coat) In progress
11 Water proofing works in sump In progress

JANUARY

  17 Jan 2019

Terrace floor slab concreting Completed
Terrace floor column concreting Completed
Block work from third to Eighteenth floor Completed
Ceiling plastering from third to Eighteenth floor Completed
External plastering
Rear side up to 11th floor - Completed
12th to terrace floor - In progress
Left side up to 11th floor - Completed
Right side up to 11th floor- Completed
Duct works
- Left side up to 11th floor -Completed
- Right side up to 11th floor -Completed
Rear side -Completed
Internal wall plastering
- 5th to 10th floor -Completed
- 11th Floor -In progress
Electrical wall chasing works
- 4th to 11th floor -Completed
- 3rd Floor In progress

Carpentry works In progress
Balcony handrail fabrication works In progress

November

  21 Nov 2018

First to eighteenth floor slab concreting Completed
Eighteenth floor column concreting 40% completed
Block work from third to Fourteenth floor Completed
Ceiling plastering from third to fifteenth floor Completed
External plastering
- Rear side up to 11th floor - In progress
- Left side up to 11th floor - Completed
- Right side up to 11th floor - 85% completed
Duct works
- Left side up to 11th floor, Right side up to 11th floor -Completed
Internal wall plastering up to 11th floor -45% completed
Electrical wall chasing works up to 11th floor - 35% completed

September

  06 Oct 2018

1 First to fifteenth floor slab concreting Completed
2 Fourteenth floor column concreting Completed
3 Block work from third to Eleventh floor Completed
4 Ceiling plastering from third to thirteenth floor Completed
5 External plastering
- Rear & left side In progress
6 Duct works
- Left side -Completed
- Right side -In progress


JULY

  14 Jul 2018

Foundation works Completed
First to Eleventh floor slab concreting Completed
Eleventh floor column concreting Completed
Twelfth floor slab concreting Completed

JUNE

  26 Jun 2018

Foundation works Completed
First to Tenth floor slab concreting Completed
Tenth floor column concreting Completed
Eleventh floor slab concreting Completed

MAY

  15 May 2018

1 Foundation works Completed
2 First to Nineth floor slab concreting Completed
3 Nineth floor column concreting Completed
4 Tenth floor slab concreting Completed

APRIL

  17 Apr 2018

Foundation works Completed
Seventh floor column concreting Completed
First to eighth floor slab concreting Completed

MARCH

  20 Mar 2018

1 Foundation works Completed
2 First to seventh floor slab concreting Completed

February

  02 Feb 2018

Work description Current Status
1 Foundation works Completed
2 First to fifth floor slab concreting Completed
3 Fifth floor column concreting Completed
4 Sixth floor slab shuttering & reinforcement laying works In progress

December

  16 Dec 2017

1 Foundation works Completed
2 First to third floor slab concreting Completed
3 Fourth floor slab shuttering works In progress

August

  11 Aug 2017

1 Piling works Completed
2 Pile cap & grade beam works Completed
3 Ground floor column concreting Completed
4 Ground floor roof slab concreting In Progress

01.07.2017

  01 Jul 2017

1 Piling works Completed
2 Pile chipping works Completed
3 Pile cap & grade beam works 50% completed

05.05.2017

  11 May 2017

1 Piling works Completed
2 Pile chipping works In progress

05.04.2017

  05 Apr 2017

Piling works 60% completed

04.01.2017

  04 Jan 2017

1 Piling works- Commenced
2 Pile load test - Completed