Project Details

CORDIAL ADITHYA

Ambalamukku, Trivandrum

The luxury apartment project is situated at Ambalamukku, which is one among city`s prime localities. The apartment has all modern amenities to provide the most luxurious life style in a serene atmosphere. Closeness and easy accessibility to major educational institutions, collectorate, Shopping centres, Hospitals and other essential services makes the project even more attractive and is also well connected by road, rail and air routes. Cordial Adithya comprises of subbasement, basement, ground + 17 upper floors and hence ensures a modern life style.

  • General
    Elegant lobby with Furnished reception area
    Provision for Terrace party area
    Fully furnished air-conditioned guest suite
    Provision for Internet connectivity for each apartment
    Fitness centre with most modern equipments
    A/C multi - purpose hall
    Intercom facility in all apartments
    Children`s play area
    Provision for cable TV connection in each apartment
    Individual letter box and name board
    Generator back-up for lifts, water pumps, common lighting and designated points in each apartment
    Sewage treatment system
    Provision for security
    Water supply system through sump and over head tank
    Changing room for drivers & servants
    Toilets for drivers & servants
    Automatic gate control system for entry/exit
    Individual water meter system for each apartment
    Servant maids toilet in each floor
    Solar assisted lighting in the common area
  • Specification
    Structure

    RCC framed structure designed for higher consideration with foundation

    Flooring

    Superior quality Granite flooring in entrance lobby. Elegant Vitrified tiles(2`x2`) for the remaining area, except toilets and staircases.

    Painting

    Premium quality putty with plastic emulsion for internal walls & ceiling.

    Cornice

    Cornice in living and dining.

    Toilets

    Premium quality anti skid ceramic tiles for the floor and modern glazed tiles for wall up to door height. Geyser provision and health faucet in all toilets except in servant`s toilet.

    Sanitary ware & CP fittings

    Branded sanitary fixtures matching with tiles, wall mount closet of American Standards/Roca or equivalent type with concealed flushing system. CP fitting of `Jaquar` or equivalent type except in servant`s toilet.

    Kitchen & Work Area

    Counter with granite top and single bowl stainless steel sink with drain board in kitchen. Glazed tiles above the counter to a height of 40cms. Single sink with granite top in work area. Provision for water purifier and dish washer.

    Doors

    Polished teakwood frame and shutter for entrance door and moulded shutters for internal doors with hard wood frames. Hardwood frames with flush door of one side resin coating for toilets.

    Windows

    Powder coated aluminium frame with glazed shutters and MS safety grills.

    Electrical

    All wiring with superior quality copper wires inside apartments including PVC conduits of ISI standards. Power plugs with adequate light and fan points. Points controlled by ELCB and MCB with independent KSEB metre. Branded modular switches of Legrand or equivalent quality. Provision for Washing machine, Fridge etc. and provision for internet connection in one bed room.

    Generator

    Generator backup for elevators, common lighting, water pumps and designated points in each apartment.

    Elevators

    Two numbers fully automatic elevators including one bed type.

    Cable TV

    Provision for connection in Living and master bedroom (subject to prevailing Government rules).

    Telephone

    Wiring for telephone in Living and Master bedroom.

    Water supply

    Water supply arrangements through sump and overhead tank.

    Air-Conditioning

    Electrical provision in all bedroom as per rules.

    Fire safety

    Fire protection systems as per rules.

    Car parking

    Covered car parking (at extra cost).
  • Location Map
    LOCATION MAP

WORKS ALL COMPLETED

  25 Dec 2020

ALL WORKS COMPLETED
OCCUPANCY CERTIFICATE RECEIVED ON 29.12.2019

JANUARY

  17 Jan 2019

Electrical wire pulling of apartments 95% completed
Fire fighting works (piping & fabrication works) 95% completed
Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
Sample apartment works (B type) as per brochure(except interior works & final coat painting) Completed
Tiling works
- A & B type apartments -95% completed
- C type apartments -95% completed
- D type apartments -90% completed
- Lobby & staircase area -90% completed
- Recreation floor -80% completed

Electrical HT
– Panel mounting works -Completed
- Cable pulling works 85% completed

Sewage treatment plant works 95% completed
Internal Putty works of A and B type apartments (second coat) all apartments -Completed

External primer application
- Front side, right side, left side-Completed
- Rear side -95% completed
MS window grill making & fixing of
- A , B, C & D type apartments up to 16th floor
- Completed
Aluminium window & ventilator fixing of
- A, B,C & D type apartment up to 16th floor-Completed
Lift installation works
– bed lift-Completed
– 8 passenger lift -80% completed
Inside wall plastering works -Completed
False ceiling works
- Toilets-90% completed
- Lobby area - 30% completed

Door polishing works - In progress
Internal painting of apartments (first coat)
- A & B type apartments-90% completed
- C & D type apartments - 70% completed
Carpentry works
- A & B type apartments-Completed
- C type apartments -90% completed
- D type apartments 75% completed
Lift cladding works 90% completed
External texture paint works 40% completed
Electrical switch fixing in apartments
- A & B type-70% completed
- C & D type - 40 % completed



November

  21 Nov 2018

Electrical wire pulling of apartments 95% completed
Plumbing duct works
- A, B, C & D type apartments -Completed
-Water meter duct installation -Completed
Wall chasing for plumbing works up to seventeenth floor Completed
Fire fighting works (piping & fabrication works) 90% completed
Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
Sample apartment works (B type) as per brochure(except interior works & final coat painting) Completed
Tiling works
- A , B & C type apartments -95% completed
- D type apartments -60% completed
- Lobby & staircase area -90% completed

Electrical HT
– Panel mounting works - Completed
- Cable pulling works- 65% completed

Sewage treatment plant works 85% completed
Internal Putty works of A and B type apartments (second coat) up to 16h floor -Completed
- C type apartments - 90 % completed
- D type apartments 60% completed

External primer application
- Front side, right side, left side -Completed
- Rear side -95% completed
MS window grill making & fixing of
- A , B, C & D type apartments up to 16th floor - Completed

Aluminium window & ventilator fixing of
- A, B,C & D type apartment up to 16th floor - Completed
Lift installation works
– bed lift -Completed
8 passenger lift -80% completed

Inside wall plastering works
- Apartment floors, Ground floor, Basement floors (-1 & -2) -Completed

False ceiling works – box works 85% completed
Internal primer application
- A , B, C & D type apartments 90% completed

Internal painting of A & B type apartments (first coat) 90% completed
Carpentry works
- A & B type apartments -Completed
- C type apartments 70% completed
- D type apartments 60% completed
Lift cladding works 90% completed
External texture paint works 40% completed
Electrical switch fixing in apartments 50% completed

September

  06 Oct 2018

Electrical wire pulling of apartments 95% completed
Plumbing duct works
- A, B, C & D type apartments -Completed
-Water meter duct installation -80 % completed
Wall chasing for plumbing works up to seventeenth floor Completed
Fire fighting works (piping & fabrication works) 90% completed
Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
Sample apartment works (B type) as per brochure(except interior works & final coat painting) Completed
Tiling works
- A & B type apartments -95% completed
- C type apartments -75% complete
- D type apartments (first coat) -20% completed

Electrical HT
– Panel mounting works Completed
- Cable pulling works 60% completed
Sewage treatment plant works 85% completed
Balcony handrail fixing 95% completed
Water proofing works in toilets & balcony up to 16th floor Completed
Staircase handrail fixing
- fire stair , main stair -Completed
Internal Putty works of A and B type apartments (second coat) up to 16h floor-Completed
- C type apartments - 70 % completed
- D type apartments - 50 % completed

External primer application
- Front side, right side, left side-Completed
- Rear side -95% completed
MS window grill making & fixing of
- A , B, C & D type apartments up to 16th floor - Completed
Aluminium window & ventilator fixing of
- A, B,C & D type apartment up to 16th floor Completed
Lift installation works
– bed lift -Completed
8 passenger lift -In progress
Inside wall plastering works
- Apartment floors -Completed
- Ground floor -90% completed
- Basement floors (-1 & -2) - Completed
False ceiling works – box works 85% completed
Internal primer application
- A & B type apartments 80% completed
- Internal painting of A & B type apartments (first coat) 45% completed
Carpentry works
- A & B type apartments-Completed
- C type apartments 65% completed
- D type apartments 50% completed

JULY

  14 Jul 2018

Electrical wire pulling of apartments 85% completed
Plumbing duct works - A, B, C & D type apartments -Completed
Plumbing -Water meter duct installation -50 % completed
Wall chasing for plumbing works up to seventeenth floor Completed
Fire fighting works 75% completed
Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
Sample apartment works B type 95% completed
Tiling works A & B type apartments -80% completed
Tiling works - C type apartments -20% completed
Electrical HT – Panel mounting works 75% completed
Outside wall plastering work Completed
Sewage treatment plant works 75% completed
Balcony handrail fixing 95% completed
Water proofing works in toilets & balcony up to 16th floor (except D type) Completed
Staircase handrail fixing - fire stair, main stair Completed
Internal Putty works of A and B type apartments (second coat) up to 16h floor Completed
External primer application - Front side, right side, left side Completed
External primer application - Rear side -95% completed
MS window grill making & fixing of A , B & C type apartments up to 16th floor -95% completed
- D type apartments -50% completed
Aluminium window fixing of - A, B & C type apartment up to 16th floor -95% completed
- D type apartments -60% completed
Lift installation works – bed lift - Completed
8 passenger lift--In progress
Inside wall plastering works
- Apartment floors, Basement floors- Completed
- Ground floor-In progress
False ceiling works – box works 65% completed
Internal primer application
- A & B type apartments
70% completed

JUNE

  26 Jun 2018

Electrical wire pulling of apartments 60% completed
Plumbing duct works
-A, B & C type apartments : -Completed
-D type apartments :- 25% completed
Wall chasing for plumbing works up to seventeenth floor Completed
Fire fighting works up to seventeenth floor Completed
Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
Sample apartment works B type 95% completed
Tiling works of A & B type apartments 50% completed
Electrical - HT lightning arrestor works & earthing works 75% completed
Outside wall plastering work Completed
Sewage treatment plant works In progress
Balcony handrail fixing 95% completed
Water proofing works in toilets & balcony up to 16th floor (except D type) Completed
Staircase handrail fixing
- fire stair : Completed
- main stair : 80% completed
Internal Putty works (second coat) up to 16h floor Completed
External primer application
- Front side,right side,left side: Completed
- Rear side : 50% completed
MS window grill making & fixing of
- A & B type apartments up to 16th floor Completed
- C type apartments up to 10th floor Completed
Aluminium window fixing of
- A & B type apartment up to 16th floor Completed
- C type apartments up to 10th floor Completed

Lift installation works – one lift Completed
Inside wall plastering works 80% completed
False ceiling works – box works 25% completed

APRIL

  17 Apr 2018

Electrical wire pulling of apartments 35% completed
Plumbing duct works
1. A type apartments -95% completed
2. B type apartments - 35% completed
Wall chasing for plumbing works up to sixteenth floor Completed
Fire fighting works up to sixteenth floor Completed
Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
Sample apartment works B type 95% completed
Ceiling plastering & Internal wall plastering of apartments Completed
Electrical - HT cable tray works in ducts Completed
Outside wall plastering work completed
Teak wood entrance door shutter making and fixing in apartments Completed
Balcony handrail fixing 90% completed
Water proofing works in toilets up to 13th floor Completed
Staircase handrail fixing
- fire stair Completed
- main stair 15% completed
Internal Putty works (second coat) up to 16h floor Completed
External primer application completed
Water proofing works in balconies 60% completed
MS window grill making & fixing up to 10th floor Completed
Aluminium window fixing of A & B type apartment up to 10th floor Completed
Lift installation works 80% completed

MARCH

  20 Mar 2018

1 Electrical wire pulling of apartments 25% completed
2 Plumbing duct works of A type apartments 95% completed
3 Wall chasing for plumbing works up to fourteenth floor Completed
4 Fire fighting works up to fourteenth floor Completed
5 Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
6 Sample apartment works B type 80% completed
7 Ceiling plastering & Internal wall plastering of apartments Completed
8 Electrical - HT cable tray works 15% completed
9 Outside wall plastering work
1. Front side - Completed
2. right side - Completed
3. left side - Completed
4. Rear side 25% completed
10 Teak wood entrance door shutter making and fixing 90% Completed
11 Balcony handrail fixing 80% completed
12 Water proofing works in toilets up to 13th floor Completed
13 Staircase handrail fixing for fire stair Completed
14 Internal Putty works up to 13h floor Completed
15 External primer application
- Front side Completed

- right side Completed
- left side Completed
- Rear side 90% completed

-
-
16 Water proofing works in balconies 60% completed
17 Window grill making & fixing 25% completed
18 Aluminium window fixing of B type apartment up to 10th floor Completed
19 Lift installation works 25% completed

February

  10 Feb 2018

Structural works of building Completed
Ceiling plastering up to machine room roof Completed
Electrical wall chasing of all apartments Completed
Wall chasing for plumbing works up to fourteenth floor Completed
Fire fighting works up to fourteenth floor Completed
Sample apartment works as per brochure(except interior works & final coat painting) Completed
Internal wall plastering up to sixteenth floor Completed
Electrical - HT works In progress
Teak wood entrance door shutter making and fixing 70% Completed
Balcony handrail fixing 80% completed
Water proofing works in toilets up to 9th floor Completed
Staircase handrail fixing for fire stair up to 14th floor Completed
Internal Putty works up to 10h floor Completed
Outside wall plastering work
Front side - Completed
right side - Completed
left side - 70% Completed
Rear side - In progress
External primer application
Front side - Completed
right side, left side, Rear side - 90% completed





December

  15 Dec 2017

1 Sub basement roof to machine room roof slab concreting Completed
2 Ceiling plastering up to sixteenth floor Completed
3 Block work up to sixteenth floor Completed
4 Electrical wall chasing up to fifteenth floor Completed
5 Wall chasing for plumbing works up to eighth floor Completed
6 Fire fighting works up to eleventh floor Completed
7 Sample apartment works 85% completed
8 Internal wall plastering up to twelfth floor Completed
9 Outside wall plastering work - Front side completed, right side 65% completed
10 Door frame fixing Completed
11 Balcony handrail fixing 60% completed
12 Plastering works inside lifts Completed

NOVEMBER 2017

  04 Nov 2017

1 Sub basement roof to machine room roof slab concreting Completed
2 Over head water tank concreting works Completed
3 Ceiling plastering up to sixteenth floor Completed
4 Block work up to sixteenth floor Completed
5 Electrical wall chasing up to fourteenth floor Completed
6 Plumbing works up to seventh floor Completed
7 Fire fighting works up to eleventh floor Completed
8 Sample apartment works 70% completed
9 Internal wall plastering up to ninenth floor Completed
10 Outside wall plastering work In progress
11 Retaining wall concreting 80% completed

August

  11 Aug 2017

1 Sub basement roof to seventeenth floor slab concreting Completed
2 Sixteenth floor column concreting Completed
3 Ceiling plastering up to fifteenth floor Completed
4 Block work up to thirteenth floor Completed
5 Electrical wall chasing up to fifth floor Completed
6 Core cutting work for plumbing up to tenth floor Completed
7 Sample apartment works 70% completed
8 Internal wall plastering up to fifth floor Completed
9 Retaining wall concreting 80% completed

01.07.2017

  01 Jul 2017

1 Sub basement roof to seventeenth floor slab concreting Completed
2 Sixteenth floor column concreting Completed
3 Ceiling plastering up to fifteenth floor Completed
4 Block work up to thirteenth floor Completed
5 Electrical wall chasing up to fifth floor Completed
6 Core cutting work for plumbing up to tenth floor Completed
7 Sample apartment works 60% completed
8 Internal wall plastering up to fifth floor Completed
9 Retaining wall concreting In progress

05.05.2017

  11 May 2017

1 Sub basement roof to fifteenth floor slab concreting Completed
2 Fifteenth floor column concreting Completed
3 Sixteenth floor slab concreting 50% completed
4 Ceiling plastering up to thirteenth floor Completed
5 Block work up to eleventh floor Completed
6 Electrical wall chasing up to third floor Completed
7 Core cutting work for plumbing up to tenth floor Completed
8 Sump tank concreting 75% completed
9 Sample apartment works In progress
10 Internal wall plastering up to second floor Completed

05.04.2017

  05 Apr 2017

Sub basement roof to thirteenth floor slab concreting Completed
Thirteenth floor column concreting 50% completed
Fourteenth floor slab shuttering & reinforcement laying works 50% completed
Ceiling plastering up to eleventh floor Completed
Block work up to ninenth floor Completed
Block work in ninenth floor In progress
Electrical wall chasing In progress
Core cutting work for plumbing In progress
Sump tank concreting 50% completed
Sample apartment works In progress
Internal wall plastering in first floor Completed

Work Status As On 05.03.2017

  05 Mar 2017

1 Sub basement roof to twelfth floor slab concreting Completed
2 Eleventh floor column concreting Completed
3 Twelfth floor column concreting 50% completed
4 Thirteenth floor slab shuttering & reinforcement laying works 50% completed
5 Ceiling plastering up to tenth floor Completed
6 Block work up to eighth floor Completed
7 Block work in Ninenth floor In progress
8 Electrical wall chasing In progress
9 Core cutting work for plumbing In progress
10 Sump tank concreting In progress

Work Status As On 05.02.2017

  05 Feb 2017

1 Sub basement roof to tenth floor slab concreting Completed
2 Tenth floor column concreting Completed
3 Eleventh floor slab concreting 50 % completed
4 Eleventh floor column concreting In progress
5 Eleventh floor slab shuttering & reinforcement laying works In progress
6 Ceiling plastering up to seventh floor Completed
7 Eigth floor ceiling plastering In progress
8 Block work up to sixth floor Completed
9 Block work in seventh floor In progress
10 Sump tank earthwork Completed

04.01.2017

  04 Jan 2017

1 Sub basement roof to ninenth floor slab concreting Completed
2 Ninenth floor column concreting 50 % completed
3 Tenth floor slab shuttering & reinforcement laying works In progress
4 Ceiling plastering up to fourth floor Completed
5 Fifth floor ceiling plastering In progress
6 Block work up to third floor Completed

December

  06 Dec 2016

1 Sub basement roof to seventh floor slab concreting Completed
2 Seventh floor column concreting 85 % completed
3 Eighth floor slab shuttering & reinforcement laying works 50% completed
4 Ceiling plastering up to 1st floor Completed
5 Second floor ceiling plastering In progress
6 Block work in first floor In progress

01.11.2016

  01 Nov 2016

1 Foundation works Completed
2 Sub basement roof to fourth floor slab concreting Completed
3 Fifth floor slab concreting Completed
4 Fifth floor column concreting Completed
5 Sixth floor slab shuttering & reinforcement laying works 50% completed

Cordial Adithya.jpg

JUNE 2016

  09 Aug 2016

# Work description Current Status
1 Retaining wall concreting subbasement - completed
2 Grade beam & raft slab concreting - completed
3 Column concreting sub basement floor - completed
4 Lift pit, lift wall up to sub basement floor - Completed
5 RCC ramp to subbasement - completed
6 Sub basement roof slab concreting work - completed
7 Basement floor column concreting - completed
8 Retaining wall concreting basement floor - 65% completed
9 Ground floor slab concreting - 50% completed
10 Lift wall upto ground floor - completed
11 Main staircase upto ground floor - 75% completed

May

  02 May 2016

1 Piling works Completed
2 Pile cap concreting Completed
3 Retaining wall concreting subbasement 50% completed
4 Grade beam & raft slab concreting 75% completed
5 Column concreting 75% completed
6 Lift pit, lift wall up to sub basement floor Completed
7 RCC ramp to subbasement 50% completed
8 Sub basement roof slab concreting work 50% completed

MARCH

  25 Mar 2016

1 Piling works Completed
2 Pile cap concreting 75% completed
3 Retaining wall concreting subbasement 50% completed
4 Grade beam & raft slab concreting 50% completed
5 Column concreting 50% completed
6 Lift pit, lift wall up to sub basement floor Completed
7 RCC ramp to subbasement 75% completed
8 Sub basement roof slab shuttering work In progress

25.01.2016

  25 Jan 2016

1 Piling works Completed
2 Pile cap concreting In progress
3 Pile chipping works In progress
4 Retaining wall concreting In progress
5 Grade beam & raft slab concreting In progress
6 Column concreting In progress

DECEMBER

  29 Dec 2015

Piling work completed.
Pile cap excavation in progress.

Cordial Adithya.jpg

28.10.2015

  28 Oct 2015

Piling work completed.
Pile cap excavation started.