The luxury apartment project is situated at Ambalamukku, which is one among city`s prime localities. The apartment has all modern amenities to provide the most luxurious life style in a serene atmosphere. Closeness and easy accessibility to major educational institutions, collectorate, Shopping centres, Hospitals and other essential services makes the project even more attractive and is also well connected by road, rail and air routes. Cordial Adithya comprises of subbasement, basement, ground + 17 upper floors and hence ensures a modern life style.
Electrical wire pulling of apartments 95% completed
Fire fighting works (piping & fabrication works) 95% completed
Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
Sample apartment works (B type) as per brochure(except interior works & final coat painting) Completed
Tiling works
- A & B type apartments -95% completed
- C type apartments -95% completed
- D type apartments -90% completed
- Lobby & staircase area -90% completed
- Recreation floor -80% completed
Electrical HT
– Panel mounting works -Completed
- Cable pulling works 85% completed
Sewage treatment plant works 95% completed
Internal Putty works of A and B type apartments (second coat) all apartments -Completed
External primer application
- Front side, right side, left side-Completed
- Rear side -95% completed
MS window grill making & fixing of
- A , B, C & D type apartments up to 16th floor
- Completed
Aluminium window & ventilator fixing of
- A, B,C & D type apartment up to 16th floor-Completed
Lift installation works
– bed lift-Completed
– 8 passenger lift -80% completed
Inside wall plastering works -Completed
False ceiling works
- Toilets-90% completed
- Lobby area - 30% completed
Door polishing works - In progress
Internal painting of apartments (first coat)
- A & B type apartments-90% completed
- C & D type apartments - 70% completed
Carpentry works
- A & B type apartments-Completed
- C type apartments -90% completed
- D type apartments 75% completed
Lift cladding works 90% completed
External texture paint works 40% completed
Electrical switch fixing in apartments
- A & B type-70% completed
- C & D type - 40 % completed
Electrical wire pulling of apartments 95% completed
Plumbing duct works
- A, B, C & D type apartments -Completed
-Water meter duct installation -Completed
Wall chasing for plumbing works up to seventeenth floor Completed
Fire fighting works (piping & fabrication works) 90% completed
Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
Sample apartment works (B type) as per brochure(except interior works & final coat painting) Completed
Tiling works
- A , B & C type apartments -95% completed
- D type apartments -60% completed
- Lobby & staircase area -90% completed
Electrical HT
– Panel mounting works - Completed
- Cable pulling works- 65% completed
Sewage treatment plant works 85% completed
Internal Putty works of A and B type apartments (second coat) up to 16h floor -Completed
- C type apartments - 90 % completed
- D type apartments 60% completed
External primer application
- Front side, right side, left side -Completed
- Rear side -95% completed
MS window grill making & fixing of
- A , B, C & D type apartments up to 16th floor - Completed
Aluminium window & ventilator fixing of
- A, B,C & D type apartment up to 16th floor - Completed
Lift installation works
– bed lift -Completed
8 passenger lift -80% completed
Inside wall plastering works
- Apartment floors, Ground floor, Basement floors (-1 & -2) -Completed
False ceiling works – box works 85% completed
Internal primer application
- A , B, C & D type apartments 90% completed
Internal painting of A & B type apartments (first coat) 90% completed
Carpentry works
- A & B type apartments -Completed
- C type apartments 70% completed
- D type apartments 60% completed
Lift cladding works 90% completed
External texture paint works 40% completed
Electrical switch fixing in apartments 50% completed
Electrical wire pulling of apartments 95% completed
Plumbing duct works
- A, B, C & D type apartments -Completed
-Water meter duct installation -80 % completed
Wall chasing for plumbing works up to seventeenth floor Completed
Fire fighting works (piping & fabrication works) 90% completed
Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
Sample apartment works (B type) as per brochure(except interior works & final coat painting) Completed
Tiling works
- A & B type apartments -95% completed
- C type apartments -75% complete
- D type apartments (first coat) -20% completed
Electrical HT
– Panel mounting works Completed
- Cable pulling works 60% completed
Sewage treatment plant works 85% completed
Balcony handrail fixing 95% completed
Water proofing works in toilets & balcony up to 16th floor Completed
Staircase handrail fixing
- fire stair , main stair -Completed
Internal Putty works of A and B type apartments (second coat) up to 16h floor-Completed
- C type apartments - 70 % completed
- D type apartments - 50 % completed
External primer application
- Front side, right side, left side-Completed
- Rear side -95% completed
MS window grill making & fixing of
- A , B, C & D type apartments up to 16th floor - Completed
Aluminium window & ventilator fixing of
- A, B,C & D type apartment up to 16th floor Completed
Lift installation works
– bed lift -Completed
8 passenger lift -In progress
Inside wall plastering works
- Apartment floors -Completed
- Ground floor -90% completed
- Basement floors (-1 & -2) - Completed
False ceiling works – box works 85% completed
Internal primer application
- A & B type apartments 80% completed
- Internal painting of A & B type apartments (first coat) 45% completed
Carpentry works
- A & B type apartments-Completed
- C type apartments 65% completed
- D type apartments 50% completed
Electrical wire pulling of apartments 85% completed
Plumbing duct works - A, B, C & D type apartments -Completed
Plumbing -Water meter duct installation -50 % completed
Wall chasing for plumbing works up to seventeenth floor Completed
Fire fighting works 75% completed
Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
Sample apartment works B type 95% completed
Tiling works A & B type apartments -80% completed
Tiling works - C type apartments -20% completed
Electrical HT – Panel mounting works 75% completed
Outside wall plastering work Completed
Sewage treatment plant works 75% completed
Balcony handrail fixing 95% completed
Water proofing works in toilets & balcony up to 16th floor (except D type) Completed
Staircase handrail fixing - fire stair, main stair Completed
Internal Putty works of A and B type apartments (second coat) up to 16h floor Completed
External primer application - Front side, right side, left side Completed
External primer application - Rear side -95% completed
MS window grill making & fixing of A , B & C type apartments up to 16th floor -95% completed
- D type apartments -50% completed
Aluminium window fixing of - A, B & C type apartment up to 16th floor -95% completed
- D type apartments -60% completed
Lift installation works – bed lift - Completed
8 passenger lift--In progress
Inside wall plastering works
- Apartment floors, Basement floors- Completed
- Ground floor-In progress
False ceiling works – box works 65% completed
Internal primer application
- A & B type apartments
70% completed
Electrical wire pulling of apartments 60% completed
Plumbing duct works
-A, B & C type apartments : -Completed
-D type apartments :- 25% completed
Wall chasing for plumbing works up to seventeenth floor Completed
Fire fighting works up to seventeenth floor Completed
Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
Sample apartment works B type 95% completed
Tiling works of A & B type apartments 50% completed
Electrical - HT lightning arrestor works & earthing works 75% completed
Outside wall plastering work Completed
Sewage treatment plant works In progress
Balcony handrail fixing 95% completed
Water proofing works in toilets & balcony up to 16th floor (except D type) Completed
Staircase handrail fixing
- fire stair : Completed
- main stair : 80% completed
Internal Putty works (second coat) up to 16h floor Completed
External primer application
- Front side,right side,left side: Completed
- Rear side : 50% completed
MS window grill making & fixing of
- A & B type apartments up to 16th floor Completed
- C type apartments up to 10th floor Completed
Aluminium window fixing of
- A & B type apartment up to 16th floor Completed
- C type apartments up to 10th floor Completed
Lift installation works – one lift Completed
Inside wall plastering works 80% completed
False ceiling works – box works 25% completed
Electrical wire pulling of apartments 35% completed
Plumbing duct works
1. A type apartments -95% completed
2. B type apartments - 35% completed
Wall chasing for plumbing works up to sixteenth floor Completed
Fire fighting works up to sixteenth floor Completed
Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
Sample apartment works B type 95% completed
Ceiling plastering & Internal wall plastering of apartments Completed
Electrical - HT cable tray works in ducts Completed
Outside wall plastering work completed
Teak wood entrance door shutter making and fixing in apartments Completed
Balcony handrail fixing 90% completed
Water proofing works in toilets up to 13th floor Completed
Staircase handrail fixing
- fire stair Completed
- main stair 15% completed
Internal Putty works (second coat) up to 16h floor Completed
External primer application completed
Water proofing works in balconies 60% completed
MS window grill making & fixing up to 10th floor Completed
Aluminium window fixing of A & B type apartment up to 10th floor Completed
Lift installation works 80% completed
1 Electrical wire pulling of apartments 25% completed
2 Plumbing duct works of A type apartments 95% completed
3 Wall chasing for plumbing works up to fourteenth floor Completed
4 Fire fighting works up to fourteenth floor Completed
5 Sample apartment works (A type) as per brochure(except interior works & final coat painting) Completed
6 Sample apartment works B type 80% completed
7 Ceiling plastering & Internal wall plastering of apartments Completed
8 Electrical - HT cable tray works 15% completed
9 Outside wall plastering work
1. Front side - Completed
2. right side - Completed
3. left side - Completed
4. Rear side 25% completed
10 Teak wood entrance door shutter making and fixing 90% Completed
11 Balcony handrail fixing 80% completed
12 Water proofing works in toilets up to 13th floor Completed
13 Staircase handrail fixing for fire stair Completed
14 Internal Putty works up to 13h floor Completed
15 External primer application
- Front side Completed
- right side Completed
- left side Completed
- Rear side 90% completed
-
-
16 Water proofing works in balconies 60% completed
17 Window grill making & fixing 25% completed
18 Aluminium window fixing of B type apartment up to 10th floor Completed
19 Lift installation works 25% completed
Structural works of building Completed
Ceiling plastering up to machine room roof Completed
Electrical wall chasing of all apartments Completed
Wall chasing for plumbing works up to fourteenth floor Completed
Fire fighting works up to fourteenth floor Completed
Sample apartment works as per brochure(except interior works & final coat painting) Completed
Internal wall plastering up to sixteenth floor Completed
Electrical - HT works In progress
Teak wood entrance door shutter making and fixing 70% Completed
Balcony handrail fixing 80% completed
Water proofing works in toilets up to 9th floor Completed
Staircase handrail fixing for fire stair up to 14th floor Completed
Internal Putty works up to 10h floor Completed
Outside wall plastering work
Front side - Completed
right side - Completed
left side - 70% Completed
Rear side - In progress
External primer application
Front side - Completed
right side, left side, Rear side - 90% completed
1 Sub basement roof to machine room roof slab concreting Completed
2 Ceiling plastering up to sixteenth floor Completed
3 Block work up to sixteenth floor Completed
4 Electrical wall chasing up to fifteenth floor Completed
5 Wall chasing for plumbing works up to eighth floor Completed
6 Fire fighting works up to eleventh floor Completed
7 Sample apartment works 85% completed
8 Internal wall plastering up to twelfth floor Completed
9 Outside wall plastering work - Front side completed, right side 65% completed
10 Door frame fixing Completed
11 Balcony handrail fixing 60% completed
12 Plastering works inside lifts Completed
1 Sub basement roof to machine room roof slab concreting Completed
2 Over head water tank concreting works Completed
3 Ceiling plastering up to sixteenth floor Completed
4 Block work up to sixteenth floor Completed
5 Electrical wall chasing up to fourteenth floor Completed
6 Plumbing works up to seventh floor Completed
7 Fire fighting works up to eleventh floor Completed
8 Sample apartment works 70% completed
9 Internal wall plastering up to ninenth floor Completed
10 Outside wall plastering work In progress
11 Retaining wall concreting 80% completed
1 Sub basement roof to seventeenth floor slab concreting Completed
2 Sixteenth floor column concreting Completed
3 Ceiling plastering up to fifteenth floor Completed
4 Block work up to thirteenth floor Completed
5 Electrical wall chasing up to fifth floor Completed
6 Core cutting work for plumbing up to tenth floor Completed
7 Sample apartment works 70% completed
8 Internal wall plastering up to fifth floor Completed
9 Retaining wall concreting 80% completed
1 Sub basement roof to seventeenth floor slab concreting Completed
2 Sixteenth floor column concreting Completed
3 Ceiling plastering up to fifteenth floor Completed
4 Block work up to thirteenth floor Completed
5 Electrical wall chasing up to fifth floor Completed
6 Core cutting work for plumbing up to tenth floor Completed
7 Sample apartment works 60% completed
8 Internal wall plastering up to fifth floor Completed
9 Retaining wall concreting In progress
1 Sub basement roof to fifteenth floor slab concreting Completed
2 Fifteenth floor column concreting Completed
3 Sixteenth floor slab concreting 50% completed
4 Ceiling plastering up to thirteenth floor Completed
5 Block work up to eleventh floor Completed
6 Electrical wall chasing up to third floor Completed
7 Core cutting work for plumbing up to tenth floor Completed
8 Sump tank concreting 75% completed
9 Sample apartment works In progress
10 Internal wall plastering up to second floor Completed
Sub basement roof to thirteenth floor slab concreting Completed
Thirteenth floor column concreting 50% completed
Fourteenth floor slab shuttering & reinforcement laying works 50% completed
Ceiling plastering up to eleventh floor Completed
Block work up to ninenth floor Completed
Block work in ninenth floor In progress
Electrical wall chasing In progress
Core cutting work for plumbing In progress
Sump tank concreting 50% completed
Sample apartment works In progress
Internal wall plastering in first floor Completed
1 Sub basement roof to twelfth floor slab concreting Completed
2 Eleventh floor column concreting Completed
3 Twelfth floor column concreting 50% completed
4 Thirteenth floor slab shuttering & reinforcement laying works 50% completed
5 Ceiling plastering up to tenth floor Completed
6 Block work up to eighth floor Completed
7 Block work in Ninenth floor In progress
8 Electrical wall chasing In progress
9 Core cutting work for plumbing In progress
10 Sump tank concreting In progress
1 Sub basement roof to tenth floor slab concreting Completed
2 Tenth floor column concreting Completed
3 Eleventh floor slab concreting 50 % completed
4 Eleventh floor column concreting In progress
5 Eleventh floor slab shuttering & reinforcement laying works In progress
6 Ceiling plastering up to seventh floor Completed
7 Eigth floor ceiling plastering In progress
8 Block work up to sixth floor Completed
9 Block work in seventh floor In progress
10 Sump tank earthwork Completed
1 Sub basement roof to ninenth floor slab concreting Completed
2 Ninenth floor column concreting 50 % completed
3 Tenth floor slab shuttering & reinforcement laying works In progress
4 Ceiling plastering up to fourth floor Completed
5 Fifth floor ceiling plastering In progress
6 Block work up to third floor Completed
1 Sub basement roof to seventh floor slab concreting Completed
2 Seventh floor column concreting 85 % completed
3 Eighth floor slab shuttering & reinforcement laying works 50% completed
4 Ceiling plastering up to 1st floor Completed
5 Second floor ceiling plastering In progress
6 Block work in first floor In progress
1 Foundation works Completed
2 Sub basement roof to fourth floor slab concreting Completed
3 Fifth floor slab concreting Completed
4 Fifth floor column concreting Completed
5 Sixth floor slab shuttering & reinforcement laying works 50% completed
# Work description Current Status
1 Retaining wall concreting subbasement - completed
2 Grade beam & raft slab concreting - completed
3 Column concreting sub basement floor - completed
4 Lift pit, lift wall up to sub basement floor - Completed
5 RCC ramp to subbasement - completed
6 Sub basement roof slab concreting work - completed
7 Basement floor column concreting - completed
8 Retaining wall concreting basement floor - 65% completed
9 Ground floor slab concreting - 50% completed
10 Lift wall upto ground floor - completed
11 Main staircase upto ground floor - 75% completed
1 Piling works Completed
2 Pile cap concreting Completed
3 Retaining wall concreting subbasement 50% completed
4 Grade beam & raft slab concreting 75% completed
5 Column concreting 75% completed
6 Lift pit, lift wall up to sub basement floor Completed
7 RCC ramp to subbasement 50% completed
8 Sub basement roof slab concreting work 50% completed
1 Piling works Completed
2 Pile cap concreting 75% completed
3 Retaining wall concreting subbasement 50% completed
4 Grade beam & raft slab concreting 50% completed
5 Column concreting 50% completed
6 Lift pit, lift wall up to sub basement floor Completed
7 RCC ramp to subbasement 75% completed
8 Sub basement roof slab shuttering work In progress
1 Piling works Completed
2 Pile cap concreting In progress
3 Pile chipping works In progress
4 Retaining wall concreting In progress
5 Grade beam & raft slab concreting In progress
6 Column concreting In progress