Project Details

Second Annexe Building

Statue, Trivandrum

Proposed to be housed in 1.31 acres of land
RC estimate – Rs 40 Crs submitted to Govt. on Dec. 2010. Administrative sanction accorded by Govt. on Jan.2011.Foundation stone laid by the then C.M on 09.02.2011.The proposed building consists of four blocks.The first 3 blocks have nine floors including cellar. The 4th block has only 4 floors including cellar.The total plinth area is 16135.66 m2.
The new Govt. sanctioned Rs 1.90 Cr for strengthening the foundation of 4th block to G+7.
The cost of construction is 44.90 Cr

  • Amenities
    1. Ground Floor- 2145.94m2
    >Lawn
    >Vehicle parking – cars:- 40 nos; two wheelers:- 70 nos.
    >Porch,
    >Lobby,
    >Reception,
    >Visitors Lounge,
    >Administration offices, and toilet blocks
    >Treasury,
    >ATMs,
    >Mechanical Rooms,
    >Electrical rooms,
    2. First Floor – 2067.07m2
    >Minister’s office,
    >VIP waiting Room,
    >Rest-room,
    >Mini conference hall (80 capacity)
    >Private Secretary and Addl P S Offices,
    >Budget wing,
    >Planning area,
    >ladies dinning room and ladies room,
    >toilet block (ladies and gents)
    3. Second Floor- 2024.49m2
    >Secretaries offices
    >Joint Secretaries offices,
    >Under Secretaries offices,
    >Offices for education loan
    >Pension, nodal and establishment,
    >IT division,
    >Guest Room and Guest Dinning
    >Stairs 6nos and lifts 9 nos. Toilet block ( L & G)
    4. Third Floor- 1543.74 m2
    >Principal Secretaries offices,
    >Joint Secretaries offices,
    >Addl Secretary offices,
    >Deputy Secretaries offices
    >Under Secretaries offices
    >Stairs 6nos and lifts 7nos. Toilet block ( L & G)
    5. Fourth Floor – 1466.62 m2
    >Principal Secretaries offices,
    >Joint Secretaries offices,
    >Addl Secretary offices,
    >Deputy Secretaries offices
    >Under Secretaries offices
    >Stairs 6nos and lifts 7nos. Toilet block ( L & G)
    6. Fifth Floor:-1510.50 m2
    >Secretaries offices
    >Superintendants offices,
    >cashiers offices,
    >Space for Peons,
    >Stationary & despatch
    >Toilet block ( L & G)
    >Stairs 4nos and lifts 7nos
    7. Sixth Floor:- 1510.50m2
    >Secretary offices,
    >Accounts Department,
    >Industry & PW (IND – PW) Department,
    >IW-T (CTE) Department,
    >Rules & stream lining Department,
    >Secret Section,
    >Stairs 4nos and lifts 7nos Toilet block ( L & G)
    8. Seventh Floor:- 1412.36m2
    >Addl Secretaries Offices
    >Under Secretaries Offices
    >Superintendants offices,
    >Audit wing,
    >Welfare Department.
    >PF Department
    >Thapal section
    >IW- NT(A to K) Department
    >Stairs 4nos and lifts 7nos Toilet block ( L & G)
    9. Terrace Floor :-185.17 m2
    >Open Terrace,
    >Head Rooms,
    >Water storage.
    10. Machine room:- 185.17 m2
  • All Works
    All Works are executed as per IS standards and PWD Scheduled Specifications
IMG_0450.jpg

Work In Progress

  23 Mar 2017

1st block structure and masonry work completed. 2nd block structure is completd. 3rd block 1st floor slab is in progress. 4th block structure is completed

Secretariat Annexes Work In Progress

  23 Mar 2017

Block- I Structure work completed
Block- II Structure work completed
Block - III Structure work inprogress
Block-IV Structure work completed
Block I and Block II Masonry Work is Progress