Our Cordial Prabha is designed and executed at Pattom, which is the most attractive of all residential localities in the regal splendor of Trivandrum.This project comprises of B + G + 16 floors constituting 26 luxury apartments that enhances Quality Living and Lifestyle The Project enjoys close proximity to reputed Schools, Colleges, Hospitals, Worship places and Shopping centers and is well connected by Rail, Road and Air Routes
Work completed in all respects Application submitted to Thiruvananthapuram Corporation for obtaining TC nos.
1. Work completed in all respects Application submitted to Thiruvananthapuram corporation for obtaining TC nos.
Work completed in all respects Application submitted to Thiruvananthapuram corporation for obtaining TC nos.
1 Common area second coat painting In Progress
2 Final coat painting in basement, ground & first floor parking area Completed
1 Second coat painting inside apartments Completed
2 Common area second coat painting In Progress
3 Common area light fittings fixture Completed
4 Final coat painting in basement, ground & first floor parking area In Progress
5 Common area aluminium works Completed
1 Second coat painting inside apartments 90% completed
2 Common area second coat painting In Progress
3 Children’s play area work Completed
4 HT cabling work Completed
5 Final coat painting external portion of building Completed
1 Fixing CP & sanitary fittings inside apartments Completed
2 Fire fighting work Completed
3 Stair case handrail fixing fire stair Completed
4 Stair case handrail fixing main stair Completed
5 Lift Work – 8 passenger
-13 passenger Completed
Completed
6 Internal painting work
1 st coat completed, final coat
In Progress
7 Pressed tile work in ground floor Completed
8 HT cabling work In Progress
9 External painting work
1 st coat completed, final coat
In Progress
10 Main Entrance gate work Completed
11 Children’s play area work In Progress
12 Ground & First floor entrance lobby granite & false ceiling works Completed
1 Fixing CP & sanitary fittings inside apartments 90% completed
2 Fire fighting work 95% completed
3 Stair case handrail fixing fire stair In Progress
4 Stair case handrail fixing main stair 90% completed
5 Lift Work – 8 passenger
-13 passenger Completed
In progress
6 Internal painting work
1 st coat completed, final coat
In Progress
7 Pressed tile work in ground floor 95% completed
8 HT cabling work In Progress
9 External painting work
1 st coat completed, final coat
In Progress
10 Main Entrance gate work 95% completed
11 Children’s play area work In Progress
12 Ground & First floor entrance lobby granite & false ceiling works In Progress
# Work description Current Status
1 First floor ramp slab & entrance lobby slab extension works - In progress
2 Block work for apartment area - Completed
3 Block work for common area - In progress
4 Ceiling plastering - Completed
5 Internal & External wall plastering - Completed
6 Outside primer work A & B apartments - Completed
7 Electrical wall chasing - Completed
8 Fixing CP & sanitary fittings inside apartments - In progress
9 Water line plumbing duct work - Completed
10 Fire fighting work - 90% completed
11 Fire duct work - Completed
12 Electrical wire pulling A a
pt - Completed
13 Electrical wire pulling B apt - Completed
14 Water proofing in toilets - Completed
15 Hand rail fixing in balcony - Completed
16 Stair case handrail fixing fire stair - 90% completed
17 Stair case handrail fixing main stair - 90% completed
18 Tiling work in apartments except 2A - Completed
19 Tiling work in both staircases - Completed
20 2nd coat putty work - Completed
21 Lift Work and two lifts - Completed
22 Pile cap & column work for ramp - Completed
23 Window grill fixing - Completed
24 Lift cladding work - Completed
25 Stilling chamber work - Completed
26 Drainage line work towards external chamber - Completed
27 Internal painting work - In Progress
28 Basement floor drive way earthwork - In Progress
29 Pressed tile work in first floor parking area -Completed
30 Sump tank work - Completed
31 HT cabling work - In Progress
32 External painting work - In Progress
33 Ramp work from road to ground floor slab - In Progress
1 Structural works Completed
2 Block work Completed
3 Ceiling plastering Completed
4 Internal wall plastering Completed
5 External wall plastering Completed
6 Outside primer work A & B apartments completed
7 Electrical wall chasing Completed
8 Plumbing work inside apartments Completed
9 Water line plumbing duct work Completed
10 Fire fighting work 90% Completed
11 Fire duct work Completed
12 Electrical wire pulling A apt Completed
13 Electrical wire pulling B apt Completed
14 Water proofing in toilets Completed
15 Hand rail fixing in balcony Completed
16 Stair case handrail fixing fire stair completed
17 Stair case handrail fixing main stair completed
18 Tiling work in apartments except 2A & 14C1 Completed
19 Tiling work in staircase Completed
20 2nd coat putty work up to 12th floor Completed
21 Lift Work – one lift running, 2nd lift In Progress
22 Pile cap & column work for ramp Completed
23 Window grill fixing A & B apartments up to 15th floor Completed
24 Lift cladding work Completed
25 Stilling chamber work Completed
26 STP drainage line work 80% Completed
27 Internal painting work In Progress
28 Basement floor ramp shuttering work In Progress
29 Sump tank work In Progress
30 HT cabling work Completed
1 Structural works Completed
2 Block work Completed
3 Ceiling plastering Completed
4 Internal wall plastering Completed
5 External wall plastering Completed
6 Outside primer work A & B apartments completed
7 Electrical wall chasing Completed
8 Plumbing work inside apartments Completed
9 Water line plumbing duct work Completed
10 Fire fighting work 90% Completed
11 Fire duct work 90% Completed
12 Electrical wire pulling A apt up to 15th floor Completed
13 Electrical wire pulling B apt up to 15th floor Completed
14 Water proofing in toilets Completed
15 Hand rail fixing in balcony Completed
16 Stair case handrail fixing fire stair 90% completed
17 Stair case handrail fixing main stair 90% completed
18 Tiling work in apartments up to 14th floor Completed
19 Tiling work in staircase Completed
20 2nd coat putty work up to 12th floor Completed
21 Lift Work – one lift running, 2nd lift In Progress
22 Pile cap & column work for ramp Nearing completion
23 Window grill fixing A & B apartments up to 15th floor Completed
24 Lift cladding work In Progress
25 Stilling chamber work Completed
26 STP drainage line work In Progress
27 Internal painting work In Progress
28 Basement floor ramp shuttering work In Progress
1 Structural works Completed
2 Block work Completed
3 Ceiling plastering Completed
4 Internal wall plastering Completed
5 External wall plastering Completed
6 Outside primer work A & B apts above 13th floor In progress
7 Electrical wall chasing Completed
8 Plumbing work upto 16th floor Completed
9 Water line plumbing duct work In Progress
10 Fire fighting upto 15thfloor Completed
11 Fire duct work upto 16th floor Completed
12 Electrical wire pulling A apt upto 14th floor Completed
13 Electrical wire pulling B apt upto 14th floor Completed
14 Water proofing in toilets upto 14th floor Completed
15 Hand rail fixing in balcony Completed
16 Stair case handrail fixing fire stair Completed
17 Stair case handrail fixing main stair Completed
18 Tiling work in apartments upto 12th floor Completed
19 Tiling work in staircase Completed
20 2nd coat putty work In Progress
21 Lift Work (operational aprox. by feb 10th) In Progress
22 Over head water tank wall and slab concreting Completed
23 Water proofing overhead water tank Completed
24 Piling work for ramp In Progress
1 Stair head room slab Completed
2 Block work Completed
3 Ceiling plastering Completed
4 Internal wall plastering up to 15th floor Completed
5 External plastering three sides (back & sides) Completed
6 Outside primer work A & B apt upto 12th floor Completed
7 Electrical wall chasing up to 16thfloor Completed
8 Plumbing work upto 14th floor Completed
9 Plumbing duct work upto 12th floor Completed
10 Fire fighting upto 14thfloor Completed
11 Fire duct work upto 12th floor Completed
12 Electrical wire pulling A apt upto 12th floor Completed
13 Electrical wire pulling B apt upto 12th floor Completed
14 Water proofing in toilets upto 12th floor Completed
15 Hand rail fixing in balcony upto 14th floor Completed
16 Stair case handrail fixing fire stair upto 14th floor In Progress
17 Stair case handrail fixing main stair Completed
18 Tiling work upto 10th floor Completed
19 Putty work upto 8th floor Completed
20 Lift Work In Progress
21 Over head water tank wall and slab concreting Completed
22 Water proofing overhead water tank In Progress
1 Stair head room slab Completed
2 Block work upto 16th floor Completed
3 Ceiling plastering upto 16th floor Completed
4 Internal wall plastering up to 14th floor Completed
5 External plastering for A & B apt 13th floor Completed
6 Outside primer work A & B apt upto 12th floor Completed
7 Electrical wall chasing up to 14thfloor Completed
8 Plumbing work upto 12th floor Completed
9 Plumbing duct work 2 to 12 A and B apts Completed
10 Fire fighting upto 10thfloor Completed
11 Fire duct work In Progress
12 Electrical wire pulling A apt upto 11th floor Completed
13 Electrical wire pulling B apt upto 11th floor Completed
14 Water proofing in toilets upto 10th floor Completed
15 Hand rail fixing in balcony upto 14th floor Completed
16 Stair case handrail fixing fire stair In Progress
17 Stair case handrail fixing main stair Completed
18 Tiling in sample apartment Completed
19 Tiling work upto 8th floor Completed
20 Putty work 7th floor
Completed
1 17th floor slab Completed
2 Block work upto 14th floor Completed
3 Ceiling plastering upto 15th floor Completed
4 Internal wall plastering up to 12th floor Completed
5 External plastering for A & B apt 12th floor Completed
6 Outside primer work A & B apt upto 12th floor Completed
7 Electrical wall chasing up to 12thfloor Completed
8 Plumbing work upto 10th floor Completed
9 Plumbing duct work In Progress
10 Fire fighting upto 8thfloor Completed
11 Electrical wire pulling A apt upto 9th floor Completed
12 Electrical wire pulling B apt upto 9th floor Completed
13 Water proofing in toilets upto 9th floor Completed
14 Hand rail fixing in balcony upto 12th floor Completed
15 Stair case handrail fixing fire stair In Progress
16 Stair case handrail fixing main stair Completed
17 Tiling in sample apartment Completed
18 Tiling work upto 7th floor Completed
1) 16th floor slab completed
2) 17th floor shuttering completed
3) block work and ceiling plastering up to 12th floor completed
4) external plastering up to 12th floor completed
5) internal plastering up to 10th floor completed
6)outside primer work apartment B side upto 12th floor completed
7)electrical wall chasing up to 11th floor completed
8) plumbing work up to 10th floor completed
1) 15th floor slab & column concreting completed
2) 16th floor shuttering work completed
3) block work up to 12th floor completed
4) ceiling plastering upto 12th floor completed
5)internal wall plastering up to 10th floor completed
6) external plastering west south side up to 12th floor completed
7) plumbing work up to 7th floor completed
8) electrical wall chasing up to 11th floor completed
9) fire fighting up to 6th floor completed
10) hand rail fixing up to 12th floor completed
11) tiling in sample apartment completed
1) 14th floor slab completed.
2) Block work upto 11th floor completed.
3) ceiling plastering up to 12th floor completed.
4) wall plastering up to 10th floor completed.
5) door frame fixing up to 11th floor completed
6) Electrical box fixing up to 11th floor completed
7) plumbing work up to 5th floor.
8)tile work and putty work started in sample apartment.
* 13th floor slab completed
*Block work upto 10th floor completed
*Ceiling plastering upto 11th floor completed
* Wall plastering upto 8th floor
* Door frame upto 9th floor completed
* Electrical wall chasing upto 9th floor completed
* Fire fighting upto 2nd floor completed
1. 12th floor slab completed.
2. Block work upto 9th floor completed.
3. Ceiling plastering upto 10th floor completed.
4. Door frame fixing upto 2nd floor completed.
5. Electrical wall chasing up to 6th floor completed.up to 4th floor completed.
CORDIAL PRABHA
1. 10th floor slab completed.
2. Block work upto 7th floor completed.
3. Ceiling plastering upto 7th floor completed.
4. Door frame fixing of sample apartment completed.
5. Electrical box fixing up to 4th floor completed.
1. 9th floor slab completed.
2. Block work upto 7th floor completed.
3. Ceiling plastering upto 7th floor completed.
4. Door frame fixing of sample apartment completed.
5. Electrical box fixing up to 4th floor completed
* 8th Floor Slab concreting Completed.
* Ceiling plastering up to 6th Floor Completed.
* Block Work up to 4th Floor Completed.
* Door frame fixing of sample apartment completed.
* Drive way slab in Ground Floor Completed.
* 7th Floor Slab casting Completed
* Ceiling plastering Completed up to 3rd Floor
* Block work completed up to 5th floor slab
6th Floor Slab concreting Completed
7th Floor Shuttering works going on
5th Floor Slab concreting Completed
6th Floor Shuttering works going on
5th Floor Slab concreting Completed
6th Floor Shuttering works going on
Concreting works
* 3rd Floor Slab Completed
* Block making Started
* Ceiling Plastering Started
* GI Wire Pulling (Electrical) Started
* Scheduled date of 4th Floor Slab-05/08/2014
* 2nd Floor Slab concreting Completed
* Basement floor ceiling plastering Completed
* 3rd Floor Shuttering works going on
* Basement Floor roof concreting completed
* Ground Floor Column concreting and Ground Floor slab works in progress
* Basement Floor roof concreting completed
* Ground Floor Column concreting and Ground Floor slab works in progress
PILE FOUNDATION COMPLETED
PILE CAP PCC WORK 25% COMPLETED
PILE CAP CONCRETE WORK IS IN PROGRESS
All preliminary site activites completed.
Site office constructed, cement storage room completed and water from bore well is completed