Project Details

Cordial Shroffs

Thycaud, Trivandrum

Typical example of urban multi dwelling unit on a very small plot of 25 cents in a high value location. Very near to Central Railway Station, Thycadu Govt: Guest House,Police Commissioner Office, Taj Residency at Trivandrum and Lord Ayappa Temple, Church, Womens College Etc. Number: of flats : 12 Recreational facilities : Yes Number of car parking : 12.



Only commercial area vacant

  • Amenities
    Internet connectivity for each apartment.
    Fitness centre.
    Intercom Facility.
    Cable TV connection in each apartment.
    Individual letter box & name board.
    Generator backup for lifts, water pumps, common lighting & designated points in each apartments.
    Provision for 24 hrs security.
    24 hrs water supply system through sump and overhead tank.
    Elegant multi purpose hall.
  • Structure
    RCC framed structure designed for higher seismic consideration with pile foundation.
    Flooring
    Superior quality Granite flooring in Entrance lobby and elegant Vitrified tiles for the remaining area except toilets.
    Painting
    Putty with premium quality plastic emulsion for internal walls and ceiling.
    Cornice
    Cornice for foyer, living, dining and master bed room.
    Toilets
    Premium quality anti skid ceramic tiles for the floor and glazed tiles for wall up to door height. Geyser provision and health faucet in all toilets except servant`s toilet.
    Sanitary ware & CP fittings
    Branded sanitary fixtures matching with tiles, wall mount closet of `American Standard` or equivalent type with concealed flushing system. CP fittings of `Jaquar` or equivalent type.
    Kitchen & Work area
    Counter with granite top and double bowl stainless steel sink in kitchen. Glazed tiles above the counter to a height of 40-cms. Single bowl sink with granite top in work area. Provision for water purifier and dish washer.
    Doors
    Polished teakwood frame and shutter for entrance door and molded shutters for internal doors with hard wood frames. Hardwood frames with paneled wooden doors for toilets.
    Windows
    Powder coated Aluminum frame with glazed shutters and MS safety grills.
    Electrical
    All wiring with superior quality copper wires including PVC conduits of ISI standards.
    Power plugs with adequate light and fan points. Points controlled by ELCB and MCB with independent KSEB metre. Branded Modular switchers of Legrand or equivalent quality.
    Provision for Washing machine, Fridge, etc and provision for internet connection for one bed room.
    Generator
    Generator backup for elevators, common lighting, water pumps and designated points in each apartment.
    Elevators
    Two numbers fully automatic elevators including one bed type.
    Cable TV
    Connection in living and master bed room(subject to prevailing Government rules).
    Telephone
    Wiring for Telephone in living and master bed room.
    Water supply
    Water supply arrangements through pump and over head tank.
    Air-Conditioning
    Provision for A/C in two bed rooms.
    Fire safety
    Fire protection systems as per rules.
    Car parking
    Covered car parking (at extra cost).
    Specification
    Structure
    RCC framed structure designed for higher seismic consideration with pile foundation.
    Flooring
    Superior quality Granite flooring in Entrance lobby and elegant Vitrified tiles for the remaining area except toilets.
    Painting
    Putty with premium quality plastic emulsion for internal walls and ceiling.
    Cornice
    Cornice for foyer, living, dining and master bed room.
    Toilets
    Premium quality anti skid ceramic tiles for the floor and glazed tiles for wall up to door height. Geyser provision and health faucet in all toilets except servant`s toilet.
    Sanitary ware & CP fittings
    Branded sanitary fixtures matching with tiles, wall mount closet of `American Standard` or equivalent type with concealed flushing system. CP fittings of `Jaquar` or equivalent type.
    Kitchen & Work area
    Counter with granite top and double bowl stainless steel sink in kitchen. Glazed tiles above the counter to a height of 40-cms. Single bowl sink with granite top in work area. Provision for water purifier and dish washer.
    Doors
    Polished teakwood frame and shutter for entrance door and molded shutters for internal doors with hard wood frames. Hardwood frames with paneled wooden doors for toilets.
    Windows
    Powder coated Aluminum frame with glazed shutters and MS safety grills.
    Electrical
    All wiring with superior quality copper wires including PVC conduits of ISI standards.
    Power plugs with adequate light and fan points. Points controlled by ELCB and MCB with independent KSEB metre. Branded Modular switchers of Legrand or equivalent quality.
    Provision for Washing machine, Fridge, etc and provision for internet connection for one bed room.
    Generator
    Generator backup for elevators, common lighting, water pumps and designated points in each apartment.
    Elevators
    Two numbers fully automatic elevators including one bed type.
    Cable TV
    Connection in living and master bed room(subject to prevailing Government rules).
    Telephone
    Wiring for Telephone in living and master bed room.
    Water supply
    Water supply arrangements through pump and over head tank.
    Air-Conditioning
    Provision for A/C in two bed rooms.
    Fire safety
    Fire protection systems as per rules.
    Car parking
    Covered car parking (at extra cost).
  • Location Map
    Location Map
IMG_0459.jpg

Work Progress

  10 Oct 2013

*** Roof slab:Sub basement to sixth floor completed.
*** Colums : Sub basement to sixth floor
*** Head room & water tank completed.
*** Lift wall concreting:Sub basement to lift machine room completed.
*** Staircase :Sub basement to sixth floor completed.
*** Staircase for lift machine room work in progress.
*** machine room floor slab & watertank slab work in progress.
*** brickwork for toilets-1st to fifth floor work in progress
*** Cealing plastering:1st floor to 5th floor completed. 6th floor work in progress.
*** blockwork: 1st to 6th floor work in progress.
*** outsidepergola & beam-1st floor level completed.
*** electric work(internal) : 1st to 5th floor work in progress.

IMG_0459.jpg

Work In Progress

  10 Oct 2013

Structure completed.
All Masonry work completed, 2nd coat putty work in all apartments completed.
Electrical work in all apartment is completed.
HT work is completed.
Transformer is installed.
Generator for supply back is installed.
Ist coat painting for interior and exterior is 90% completed.
Flooring in all apartments is completed

Work Nearing Completion

  10 Oct 2013

foundation complete
superstructure complete
masonry complete
plumbing complete
flooring complete
electricfication complete
generator setup complete
putty work complete
painting first coat complete
exterior painting first coat primer complete
lift installation is in progress

Drop an Enquiry