This Landmark project is designed to be a feather in the cap of Peroorkada, a significant location in Trivandrum city. Cordial Amity constitutes 55 luxury apartments built in an inspiring location. Amity apartments comprises of Basement + Ground + 19 Floors superstructure. Amity ensures extravagant living and is blessed with serene green surroundings. The Project enjoys close proximity to Technopark, reputed Schools, Colleges, Hospitals, Worship places and Shopping centers and is well connected by Rail, Road and Air Routes
Application submitted to Thiruvananthapuram corporation for obtaining TC nos.
Work completed. Application submitted to Thiruvananthapuram corporation for obtaining TC nos.
1 Final coat painting works inside apartments Completed
2 Recreation block final coat painting works 95% completed
1 Final coat painting works inside apartments Completed
2 Common area light fittings fixture Completed
3 Recreation block final coat painting works 95 % completed
4 Children’s play area art work Completed
5 Common area aluminium works Completed
1 Final coat painting works inside apartments 95% completed
2 Main entrance gate works Completed
3 Recreation block final coat painting works 95 % completed
4 Children’s play area art work In progress
1 Final coat painting works inside apartments 95% completed
2 Main entrance gate works Completed
3 Recreation block final coat painting works 95 % completed
4 Children’s play area art work In progress
1 Internal Plumbing works – fixing sanitary fittings Completed
2 Final coat painting works inside apartments 90% completed
3 Lift works in Main building
1. 1 st lift fully operational Completed
2. 2nd lift fully operational Completed
4 Electrical Room HT works Completed
5 External painting works (final coat) Completed
6 Sewage treatment plant –testing & commissioning Completed
7 Ground floor lobby painting work ( first coat) Completed
8 Ground floor lobby false ceiling works Completed
9 Main entrance gate works 90 % completed
10 Recreation block final coat painting works 90% completed
1 Internal Plumbing works – fixing sanitary fittings Completed
2 Final coat painting works inside apartments 85% completed
3 Lift works in Main building
1. 1 st lift fully operational
2. 2nd lift fully operational
4 Electrical Room HT works Completed
5 External painting works (final coat) Completed
6 Sewage treatment plant –testing & commissioning completed
7 Ground floor lobby painting work ( first coat) Completed
8 Compound wall & retaining wall works Completed
9 Interlock & pressed tile laying in basement floor Completed
10 RCC drain works around boundary wall Completed
11 Main entrance gate works In progress
12 Recreation block first coat painting works Completed
# Work description Current Status
1 Tiling work in A, B and C apartments (except 11B&C ) - Completed
2 Recreation block - plastering & flooring works - Completed
3 Door frame fixing - Completed
4 Internal Plumbing works and fixing sanitary fittings (except 11B & C) - Completed
5 Internal electrical works - Completed
6 Hand rail fixing in balcony (except 11B&C) - Completed
7 Fire fighting (internal work) - Completed
8 Internal Painting works except 11B& C (except final coat) - completed
9 Plumbing duct work - Completed
10 Lift works in Main building
1. 1 st lift fully operational
2. 2nd lift fully operational
11 Electrical Room HT works - 95 % completed
12 External painting works (first coat) - Completed
13 Sewage treatment plant water proofing works - Completed
14 Drive way slab work - completed
15 Basement floor plastering work - 95% completed
16 Ground floor lobby block work & plastering - Completed
17 Ground & first floor commercial area 1st coat primer - work Completed
18 Compound wall & retaining wall work south side completed, west side - 75% completed
# Work description Current Status
1 Tiling work in B and C apt up to 19th floor (except 11B&C ) Completed
2 Tiling work in A apts Completed
3 Recreation block - plastering work Completed
4 Recreation block -flooring works completed
5 Recreation block-terrace plastering works completed
6 Door frame fixing (except 11B & C) Completed
7 Internal Plumbing works – fixing sanitary fittings (except 11B & C) Completed
8 Internal electrical works except DB fixing Completed
9 Hand rail fixing in balcony (except 11A,11B&C, 2A) Completed
10 Fire fighting (internal work) Completed
11 Internal Painting works except 11B& C,11A (except final coat) completed
12 Plumbing duct work Completed
13 Lift works in Main building
1. 1 st lift fully operational
2. 2nd lift fully operational
14 Electrical Room HT works 95 % completed
15 External painting works (first coat) Completed
16 Sewage treatment plant water proofing works Completed
17 Drive way slab work 90% completed
18 Basement floor plastering work 70% completed
19 Ground floor lobby block work & plastering 70% completed
20 Ground & first floor commercial area 1st coat primer work Completed
21 Compound wall & retaining wall work south side completed, west side 60% completed
# Work description Current Status
1 Sample Apartment works Completed
2 Tiling work B and C apt up to 19th floor (except 11B&C ) Completed
3 Tiling work A apts (except 2A & 3A) Completed
4 Recreation Block structural works Completed
5 Recreation block - Block work Completed
6 Recreation block - plastering work 85% Completed
7 Door frame fixing (except 11B & C) Completed
8 Internal wall plastering Completed
9 Outside Plastering Completed
10 Internal Plumbing works Completed
11 Electrical wall chasing Completed
12 Electrical wire pulling Completed
13 Water proofing in toilets Completed
14 Hand rail fixing in balcony for A apt (except 11A, 5A & 3A) Completed
15 Hand rail fixing in balcony for B apt Completed
16 Hand rail fixing in balcony for C apt Completed
17 Fire fighting (internal work) Completed
18 Internal Painting work (1st coat) 85% completed
19 Plumbing duct work Completed
20 Over head water tank water proofing & plastering works Completed
21 Lift works in Main building
1. 1 st lift fully operational
2. 2nd lift fully operational
22 Electrical Room LT works In progress
23 External painting works (95%) Completed
24 Sump tank RCC work Completed
25 Drive way slab work In progress
1 Sample Apartment works Completed
2 Tiling work B and C apt up to 19th floor (except 11B&C & 5C) Completed
3 Tiling work A apt 9 to 19th floor 85% completed
4 Recreation Block structural works Completed
5 Recreation block - Block work Completed
6 Recreation block - plastering work 65% Completed
7 Lift machine room plastering works Completed
8 Block work in all floors Completed
9 Ceiling plastering Completed
10 Door frame fixing (except 11B & C) Completed
11 Internal wall plastering Completed
12 Outside Plastering Completed
13 Internal Plumbing works Completed
14 Electrical wall chasing Completed
15 Electrical wire pulling Completed
16 Water proofing in toilets Completed
17 Hand rail fixing in balcony for A apt (75%) Completed
18 Hand rail fixing in balcony for B apt Completed
19 Hand rail fixing in balcony for C apt Completed
20 Fire fighting (internal work) Completed
21 Putty work (1st coat) Completed
22 Plumbing duct work Completed
23 Over head water tank water proofing & plastering works Completed
24 Lift works in Main building
1. 1 st lift fully operational
2. 2nd lift erection
In progress
25 Electrical Room LT works In progress
26 Internal & External painting works (75%) Completed
27 Sump tank work In progress
28 Drive way slab work In progress
1 Sample Apartment works Completed
2 Tiling work B and C apt upto 5th floor (except 5 c) Completed
3 Recreation Block second floor slab concreting Completed
4 Recreation Block third floor slab shuttering & reinforcement laying In progress
5 Lift machine room plastering works Completed
6 Block work in all floors Completed
7 Ceiling plastering Completed
8 Door frame fixing Completed
9 Internal wall plastering Completed
10 Outside Plastering Completed
11 Internal Plumbing works Completed
12 Electrical wall chasing Completed
13 Electrical wire pulling Completed
14 Water proofing in toilets Completed
15 Hand rail fixing in balcony for A apt (75%) Completed
16 Hand rail fixing in balcony for B apt Completed
17 Hand rail fixing in balcony for C apt Completed
18 Fire fighting (internal work) Completed
19 Putty work 90% completed
20 Plumbing duct work 90% Completed
21 Over head water tank water proofing & plastering works Completed
22 Lift erection in Main building 50 % completed
23 Electrical Room LT works In progress
24 Internal & External painting works In progress
1 Sample Apartment works Completed
2 Tiling work B and C apt 10th floor Completed
3 Recreation Block first floor slab concreting Completed
4 Lift machine room plastering works Completed
5 Block work in all floors Completed
6 Ceiling plastering Completed
7 Door frame fixing Completed
8 Internal wall plastering Completed
9 Outside Plastering Completed
10 Internal Plumbing works Completed
11 Electrical wall chasing Completed
12 Electrical wire pulling Completed
13 Water proofing in toilets Completed
14 Hand rail fixing in balcony for A apt Completed
15 Hand rail fixing in balcony for B apt Completed
16 Hand rail fixing in balcony for C apt Completed
17 Fire fighting (internal work) Completed
18 Putty work 75% completed
19 Plumbing duct work 85% Completed
20 Over head water tank water proofing works Completed
21 Lift erection in Main building In progress
22 Electrical Room LT works In progress
1 Sample Apartment flooring Completed
2 Tiling work B and C apt 10th floor Completed
3 Sample Apartment interior works Completed
4 Recreation Block ground floor slab concreting Completed
5 Lift machine room roof slab Completed
6 Block work - 98% Completed
7 Ceiling plastering Completed
8 Door frame fixing all apt Completed
9 Internal wall plastering upto 19th floor Completed
10 Outside Plastering A apt – 90% and B apt – 13th floor Completed
11 Internal Plumbing work 19th floor Completed
12 Electrical wire pulling 13th floor Completed
13 Electrical wall chasing all completed Completed
14 Water proofing in toilets upto 17th floor Completed
15 Hand rail fixing in balcony for A apt upto 9th floor Completed
16 Hand rail fixing in balcony for B apt upto 13th floor Completed
17 Hand rail fixing in balcony for C apt upto 16th floor Completed
18 Fire fighting (internal work) 18th floor Completed
19 Putty work upto 16thfloor Completed
20 Plumbing duct work 15th Completed
21 Over head water tank Completed
22 Lift erection in Main building In progress
23 Electrical Room LT works In progress
1 Sample Apartment flooring Completed
2 Sample Apartment interior works Completed
3 Recreation Block ground floor slab concreting Completed
4 Lift machine room floor slab Completed
5 Block work upto 19th floor Completed
6 Ceiling plastering 19th floor Completed
7 Door frame fixing upto 19th floor Completed
8 Internal wall plastering upto 18th floor Completed
9 Outside Plastering (35%) Completed
10 Plumbing work upto 18th floor Completed
11 Electrical wire pulling upto 10th floor Completed
12 Electrical wall chasing upto 19th floor Completed
13 Water proofing in toilets upto 17th floor Completed
14 Hand rail fixing in balcony for A apt upto 8th floor Completed
15 Hand rail fixing in balcony for B apt upto 12th floor Completed
16 Hand rail fixing in balcony for C apt upto 16th floor Completed
17 Fire fighting (internal work) upto 17th floor Completed
18 Putty work upto 16thfloor Completed
19 Plumbing duct work In Progress
20 Over head water tank In Progress
1) sample apartment flooring completed
2) sample apartment interior work completed
3) recreation block ground floor slab concreting completed
4) lift machine room slab in progress
5) block work upto 16th floor completed
6) ceiling plastering up to 18th floor completed
7) door frame fixing up to 17th floor completed
8) plumbing work up to 11th floor completed
9) electrical box fixing and conduit fixing up to 16th floor completed
10) putty work up to 10th floor completed
1) Sample apartment flooring completed.
2) Sample apartment interior work in progress.
3) Recreation block in progress.
4) Block work up to 16th floor completed.
5) Ceiling plastering up to 17th floor completed.
6) 19th floor roof slab completed.
7) Door frame fixing up to 15th floor completed.
8) Plumbing work upto 11th floor.
9) Electrical box fixing and pipe laying upto 15th floor.
10)putty work 10th floor completed.
* 19th floor slab completed
* Block work upto 15th floor completed.
* Inside work plastering upto 12th floor completed
*Ceiling plastering upto 15th floor completed
* Door frame fixing upto 14th floor completed
* Plumbing work upto 9th floor completed
* Electrical work upto 13th floor completed
* Fire fighting (internal work) upto 9th completed
* Putty work 9th floor completed
* Recreation block - Ground floor column work completed
1. 17th floor slab completed.
2. Block work upto 13th floor completed.
3. Inside wall plastering upto 8th floor completed.
4. Ceiling plastering upto 14th floor completed.
5. Door frame fixing upto 12th floor completed.
6. Plumbing work upto 5th floor completed.
7. Electrical box fixing and pipe laying upto 12th floor completed.
8. Recreation block – upto plinth beam completed.
CORDIAL AMITY
1. 16th floor slab completed.
2. Block work upto 12th floor completed.
3. Inside wall plastering upto 6th floor completed.
4. Door frame fixing upto 9th floor completed.
5. Plumbing work upto 3rd floor completed.
6. Electrical box fixing and pipe laying upto 9th floor completed.
1. 16th floor slab completed.
2. Block work upto 11th floor completed.
3. Inside wall plastering upto 5th floor completed.
4. Door frame fixing upto 9th floor completed.
5. Plumbing work upto 3rd floor completed.
6. Electrical box fixing and pipe laying upto 8th floor completed.
* 13th Floor Slab RCC Completed
* Ceiling plastering Completed up to 9th Floor
* Brick work 100% completed up to 8th floor slab
* Door frame fixing completed up to 7th floor
* Inside wall plastering up to 2nd floor completed
* 7th floor electrical wall chasing completed
• 12th floor slab casting completed.
• Block work – 7th floor completed.
• Ceiling plastering – 8th floor completed.
11th Floor Slab concreting Completed
12th Floor Shuttering works on progress
11th Floor Slab concreting Completed
12th Floor Shuttering works in progress
RCC Works
1) 8TH fLoor Slab Completed
2) 9th Floor Slab completed on 16-7-14
3) 10th Floor is in progress
Masonry works
* 3rd and 4th Floor block masonry completed
* 5th Floor block masonry is nearing completion
* 6th Floor ceiling plastering is nearing completion
* 7th floor surface preparation for masonry work in progress
RCC Works
1) 8TH fLoor Slab Completed
2) 9th Floor Slab completed on 16-7-14
3) 10th Floor is in progress
Masonry works
* 3rd and 4th Floor block masonry completed
* 5th Floor block masonry is nearing completion
* 6th Floor ceiling plastering is nearing completion
* 7th floor surface preparation for masonry work in progress
RCC Works
1) 8TH fLoor Slab Completed
Masonry works
* 3rd and 4th Floor block masonry completed
* 5th Floor block masonry is nearing completion
* 6th Floor ceiling plastering is nearing completion
* 7th floor surface preparation for masonry work in progress
Sample /Mock up apartment- Masonry work completed,
Plumbing works in progress in all toilets. Painting works to be commenced.
1. 3rd floor slab concreting completed and IV slab concreting work in progress.
2. Sample Apartment works in progress
1. 3rd floor slab concreting completed and IV slab concreting work in progress.
2. Sample Apartment works in progress
Second floor slab 75% completed and the column raising above this slab is nearing completion.Work of retaining wall along left side of the building has already been started.
Earthwork and rock cutting for basement floor is completed.
Footing/foundation work - 75% completed.
Columns for the superstructure is in progress
construction upto plinth level completed
Columns of the superstructure is in progress
footing work is in progress. 50% of the footing shall be completed with 50 days
CURRENT WORK STATUS 27.09.13. Grnd Floor Slab (commercial Area) 70% completed. Colm Raising is in Progress
current level- Grnd Floor Slab (commercial Area) 70% completed. Colm Raising is in Progress. Phase II in Progress
After the completion of this slab portion, the column raising above this slab area has been started already.